Project Description

BC Hydro – Bone Creek Substation

Hanna Infrastructure achieved the design, construction, and commissioning of a 2000 sq/ft building, housing GIS switchgear for the transmission network. Located near a run-of-the-river hydroelectric facility in a mountainous valley North of Blue River, the project included site and civil works, structural steel building, cladding, fencing, and extensive electrical installations. This accomplishment highlights our proficiency in delivering comprehensive infrastructure solutions, enhancing operational efficiency in challenging environments.

ClientBC Hydro
DateDec 2010
LocationBlue River BC
Value$3,500,000

Project Description

BC TRANSMISSION CORPORATION

Hanna Infrastructure successfully replaced multiple circuit breakers and made modifications to circuit switchers in a fully operational 500-kilovolt substation. Our scope covered foundations, cable trenching, removal, and replacement of electrical equipment, ensuring seamless operations. This accomplishment underscores our proficiency in executing precise modifications within critical infrastructure, demonstrating a commitment to efficient and reliable solutions.

ClientBC Hydro
DateJun 2008
LocationQualicum and Prince George, BC
Value$850,000